Free lesson: demurrage in practice
Laytime, demurrage and dispatch, with a full worked example from contract to claim. 15 minutes, no sign-up.
Lessons are recorded in Portuguese with Portuguese subtitles. Every lesson comes with its full text in English.
Fim da aula grátis
Quer a planilha de cálculo e seguir para o curso completo?
Lessons are presented by Lia, a virtual presenter generated by AI. The content is written and reviewed by LogConsult.
Lesson text in English
0:00 Demurrage in practice. Hi, I'm Lia, the virtual presenter of LogConsult Academy. This is a free, complete lesson. In fifteen minutes, you will understand the three terms that weigh most on the bill of anyone who ships or receives cargo by vessel: laytime, demurrage and dispatch. Then we will work through a calculation together from start to finish. And at the end, you will know how to check a claim before paying it.
0:25 Why this matters. A bulk carrier sitting in port is expensive. Depending on the size and the freight market, each day of waiting can cost tens of thousands of dollars. This bill does not arrive right away. It shows up weeks after the operation, in a spreadsheet sent by the shipowner. And in most companies, no one checks this spreadsheet line by line. That is where money is lost, and that is what you will learn to avoid.
0:52 Who pays the bill. A common question is who pays this bill. The shipowner charges whoever chartered the vessel. But the cost does not have to stop there. In a soybean sale, for example, the sales contract may say that the seller reimburses demurrage at the loading port, and the buyer at the destination port. And if the delay was caused by a terminal or a supplier, the cost can be passed on to them, as long as the contracts provide for it.
1:19 Where it all begins: the contract. It all begins with the charter contract, which in the market is also called the charter party. It is the agreement between whoever has the vessel, the shipowner, and whoever has the cargo, the charterer. Besides the freight price, this contract defines the time rules: how long the vessel can stay in port, when the clock starts counting and how much each extra day costs. These clauses decide who pays for the wait.
1:44 Laytime: the agreed time. The first term is laytime. It is the time agreed in the contract to load or discharge the vessel. This time is already included in the freight price, that is, during laytime no one pays anything extra. Laytime can appear in two forms. Sometimes as a fixed number of days. Other times as an operating rate, for example, ten thousand tons per day. In that case, you divide the cargo by the rate to find out how many days you have.
2:14 How time is counted. Note that the contract also says how the days are counted. In running days, every day counts, including Sundays and holidays. In working days, Sundays and holidays are left out. And in weather working days, the hours of rain do not count, because in many ports grain is not loaded in the rain. This choice changes the result a lot. The same vessel, with the same wait, can generate a very different bill depending on this rule.
2:42 When the clock starts. Now, a question worth a lot of money: when does the clock start counting? It is not when the vessel appears on the horizon. First, the vessel needs to arrive at the port and be ready to operate. Then the master delivers a document called the notice of readiness, which in the contract appears as the notice of readiness (NOR). After delivery, there is normally a grace period of a few hours. Only when this period ends does laytime begin.
3:11 Loading and destination. A detail that changes the calculation: the operation takes place at two ports, the loading port and the destination port. Some contracts give a separate laytime for each port. Others give a single time for both, and the time saved at loading can be used at the destination. When checking, the first question is which rule the contract adopted. Calculating the two ports separately when the contract adds them together, or the reverse, produces a wrong claim.
3:39 What is left out of the calculation. Even after the clock starts, some periods can be left out of the calculation. Rain, when the contract excludes bad weather. Sundays and holidays, when the rule is working days. And stoppages caused by the vessel itself, such as a broken crane or a hold that failed inspection. Each of these exceptions needs to be written in the contract and proven by a document. Without both, it does not count.
4:06 A common case: the invalid notice. Now, a case that appears a lot. The master delivers the notice of readiness, but, on inspection, the holds are rejected for dirt or moisture. The vessel, in fact, was not ready. In many contracts, this notice is not valid, and the clock only starts after a new notice, with the vessel approved. If the claim counts the time from the first notice, it is counting hours that were not due.
4:33 Demurrage: the cost of delay. The second term is demurrage. If the operation exceeds laytime, whoever has the cargo starts paying the shipowner compensation for the extra time. This compensation is demurrage. The amount is fixed in the contract, in dollars per day. And the charge is pro rata: if half a day has passed, half of the daily amount is paid. That is why every hour counts. Four extra hours already turn into an invoice.
4:59 Once on demurrage. There is a rule that surprises many people. In several contracts, after laytime ends and demurrage begins, the exceptions stop applying. That is, the rain and the holiday, which were previously deducted, start to count normally. In the market, this is summed up in the phrase: once on demurrage, always on demurrage. Not every contract follows this rule, so it is worth reading the clause carefully before accepting or disputing a bill.
5:28 Dispatch: the reward for speed. The third term is dispatch, the good side of the story. If the operation finishes before the end of laytime, the shipowner may pay a reward for the time saved. This reward is usually half of the daily demurrage amount. Pay attention to two details. First, dispatch only exists if it is provided for in the contract. Second, in many contracts you will find the old spelling, despatch. It is the same thing.
5:57 Reading a real clause. See how this appears in writing. A typical clause says something like this: the cargo will be loaded at the rate of ten thousand tons per day, in running days, excluding periods of rain. Laytime begins six hours after the delivery of the notice of readiness. Demurrage will be paid at the rate of twenty thousand dollars per day, pro rata for fractions of a day. In three sentences, you have the rate, the counting rule, the exception, the start and the amount. These are exactly the numbers of the example we will calculate shortly.
6:32 Full example: the data. Now, let's do a complete calculation, using the clause we just read. The numbers are illustrative. A vessel will load sixty thousand tons of soybeans. The contract agrees a rate of ten thousand tons per day, in running days, not counting rain. Demurrage is twenty thousand dollars per day. And the contract provides six hours of grace after delivery of the notice of readiness. Write down these four numbers, because we will use all of them.
7:03 Step 1: how much time there is. First step: how much free time is there? Divide the cargo by the rate. Sixty thousand tons divided by ten thousand tons per day gives six days. Six days is one hundred and forty-four hours. That is the operation's laytime. As long as the time used stays within these one hundred and forty-four hours, there is no charge.
7:25 Step 2: when the clock started. Second step: when did the clock start? The master delivered the notice of readiness at eight in the morning on a Monday. Adding the six hours of grace, laytime starts at two in the afternoon on the same Monday. Notice that if someone starts counting at eight in the morning, they already gain six undue hours in the calculation. It is one of the most common errors.
7:48 Step 3: the time used. Third step: how much time was used? Loading ended one hundred and fifty-eight hours after the start of laytime. But the port bulletin records eight hours of rain, with loading stopped. Since the contract excludes rain, those eight hours come out of the calculation. The time used is one hundred and fifty-eight minus eight, that is, one hundred and fifty hours.
8:11 Step 4: the result. Fourth step: the result. One hundred and fifty hours were used against a laytime of one hundred and forty-four. Six hours over. Six hours is a quarter of a day. A quarter of twenty thousand dollars is five thousand dollars. That is the correct amount of the claim. Now, see what happens when someone gets the details wrong.
8:33 The same operation, billed wrongly. Imagine the claim arrives with two errors. The clock started at eight in the morning, without the grace period, and the rain was not deducted. The calculation goes from six to twenty hours over. In money, the claim rises from five thousand to about sixteen thousand seven hundred dollars. More than three times the correct amount, on the same operation. That is why checking is worth so much.
8:58 What this is worth per year. Now, multiply. In the example, the difference between the wrong claim and the correct one exceeded eleven thousand dollars on a single vessel. A company that ships thirty vessels a year, with similar errors on some of them, may be paying hundreds of thousands of dollars too much. And that is without counting the dispatch it failed to collect. That is why large companies have someone dedicated just to checking these bills.
9:24 And if it had finished earlier?. Now, the reverse path, with the same vessel. Imagine the loading had used only one hundred and thirty-two hours. Twelve hours of laytime would be left over, that is, half a day. If the contract provides dispatch at half of demurrage, the daily amount is ten thousand dollars. Half a day at ten thousand gives five thousand dollars, paid by the shipowner to whoever has the cargo. Many companies have this credit and do not collect it, because no one did the calculation.
9:54 How to check a claim. How do you check a claim, in practice? Gather three documents: the contract, the notice of readiness and the statement of facts, which is the port's report with everything that happened, hour by hour. Build a simple timeline, with the start and end of each event and a column saying whether that period counts or not. Then compare it with the shipowner's spreadsheet, line by line. Each difference needs to be tied to a document.
10:21 The statement of facts. The most important document in the check is the statement of facts. It lists, hour by hour, everything that happened with the vessel: the arrival, the delivery of the notice, berthing, the start and end of loading, and each stoppage with its reason. Normally, it is signed at the port by the master and by the cargo representative. That is why, if something is wrong, the best moment to record a reservation is right there, at signing.
10:48 The five points with the most errors. In the check, five points concentrate most of the errors. One: was the notice of readiness valid, with the vessel really ready? Two: was the grace period respected before the start? Three: were rain and holidays deducted as the contract says? Four: was the day-counting rule applied correctly? Five: were stoppages caused by the vessel itself left out? Keep this list. It resolves a good share of claims.
11:19 Deadlines to dispute. Another detail worth money is deadlines. Many contracts give the shipowner a deadline to submit the claim, with all the documents. If the claim arrives later, it may not even be due. On the other side, there is also a deadline for the payer to dispute. A late dispute loses strength. That is why you should note these dates as soon as the operation ends, and not leave the shipowner's spreadsheet waiting in the inbox.
11:46 Errors that appear in the spreadsheet. Beyond the contract points, the shipowner's spreadsheet also brings simple errors. Dates typed wrongly, time zones mixed up between the port and the office, the same stoppage counted twice, or a daily rate different from the one in the contract. They seem like details, but each one turns into money. The timeline you built shows these errors right away, because every hour needs to match a document.
12:11 Also on land: truck and railcar. The same logic applies on land. In road transport, the cargo transport law sets a period of up to five hours to load or unload the truck, counted from arrival at the address. After this period, the carrier is entitled to compensation per ton and per hour idle. In rail transport, the rule usually comes from the contract, which grants free time for the railcars. In all cases, whoever records the times can check the bill.
12:41 Prevention costs less. The best demurrage is the one that does not happen. Three attitudes greatly reduce waiting. First, follow the port's vessel queue every day, which the market calls the line-up, to anticipate delays. Second, make sure the cargo is at the port before the vessel arrives, because a truck or train delay on land turns into waiting at sea. Third, plan capacity for the harvest peak, not for the year's average.
13:08 How to negotiate the claim. And when you find an error, how do you negotiate? Start with the points where the proof is strongest, such as rain recorded in the bulletin and not deducted. Separate what is fact, proven by document, from what is interpretation of a clause. Facts tend to be accepted quickly and open room to discuss the rest. And record each agreed point in writing, so the conversation moves forward without going back.
13:34 Lesson summary. Now, a summary of what you learned. Laytime is the time agreed to operate the vessel, already included in the freight. If the operation exceeds that time, whoever has the cargo pays demurrage. If it finishes earlier, it may receive dispatch, as long as the contract provides for it. The clock only starts after a valid notice of readiness and the grace period. Rain, holidays and vessel stoppages may be left out. And checking every hour against a document can change the final amount a lot.
14:04 What comes in the full course. So far, you have seen the essentials. In the full course, you go further. You will see the demurrage of trucks and railcars, which follows its own rules. You will learn to prevent waiting with arrival windows and scheduling. And you will check a claim with documentary evidence, until you recover amounts and close a settlement. You finish the course with a calculator and a checking script ready to use.
14:30 Exercise: apply it now. To finish, an exercise to do today. Take a recent demurrage claim from your company. Check just two points: whether the grace period was respected and whether the rain was deducted. Redo the calculation with these two adjustments and see the difference in dollars. If you find a difference, you already know where to start: build the timeline, tie each hour to a document and present the result to the shipowner. If you find none, great: your operation is well controlled. Thank you for watching. I look forward to seeing you in the full course.